Laytime WWD (Weather Working Days) 

Legal news
Laytime provisions in a charter are most often of a fixed duration. Without any further stipulation in the express terms of the contract, laytime of a fixed duration, such as allowing four days, runs uninterrupted. It is therefore common that the charter defines how time will run. An example of this is the use of the qualification “WWD” or, in its full style, “weather working day”.

What is a “weather working day”?
The definition of “weather working day” is set out in the Laytime Definitions for Charter Parties 2013 (definitions that would apply if they are specifically agreed in the c/p). These provide as follows.

See attached file: Laytime WWD (Weather Working Days).pdf